Summit Devices Shutdown and Recovery¶
Outside the computer room numerous devices need to be powered off and subsequently recovered following a site shutdown
The following is a list of the devices that should be recovered:
First Floor: Shaft PDU + Switches
Second Floor: Computer room
Third Floor: Coating PDU + Switch, Camera Switches
Fifth Floor: Electric PDU + Switch
Auxtel: 2xAuxtel PDU + Switch
External to Building: Casino, EIE, Peñon Switches